In PMP, It is a form of planning where the work to be done in the near term is planned in detail, and future work is planned at a higher level. What?

user-image
تم إضافة السؤال من قبل Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.
تاريخ النشر: 2014/03/05
Mohammed Khan
من قبل Mohammed Khan , Principal Director Project and Program Delivery , The Options Clearing Corporation

Rolling Wave Planning (Progressive Elaboration)

Ali Ramadan
من قبل Ali Ramadan , Program Manager(MEA) , Global Knowledge

Normally it will be too costly to plan every thing from day one ,so as you go in the project we keep refining our tasks and detail it ,but from day one we know a high or even2 level plan of what will be done and when ,but details will come later on ,