ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

WHAT IS IMPORTANT FACTOR THAT HAS TO BE CONSIDERED IN RIGGING?

user-image
تم إضافة السؤال من قبل Mohammed Irfan Hassan Riaz , Sr. Project Engineer , EDAC Engineering Arabia
تاريخ النشر: 2014/03/15
moustafa thabet bakhit hasssanein ellwaky
من قبل moustafa thabet bakhit hasssanein ellwaky , Assistant HSE Manager , Al Fara'a Construction & Industrial Group - Abu Dhabi, UAE

Capacity of the hoisting equipment and working load limit which affected by few factor ,these factors are

1. Swinging Movement of Loads

2. Condition of Rigging and Hoisting Equipment

3. Weight of other equipment apart from hoisting equipment

4. Inexperience of Operators

 

Danilo Tapia
من قبل Danilo Tapia , Heavy Lift / Rigging Superintendent , aljaber heavy lift and transport

The entire lift must have a lift plan. This ensures that the job has been preplanned and all precautions have been taken to ensure the operation is completely safe. Danilo Saavedra Tapia Lifting Supervisor, Saipem Drilling Rigger1, Aramco Certified

sulthan alaudeen
من قبل sulthan alaudeen , RIGGING & HEAVY LIFTING SUPERVISOR , QNFS SHELL

Safety Awareness,  Rigging Knowledge and Experience

Naveed Iqbal
من قبل Naveed Iqbal , Safety officer , Jeong poong

1. Swinging Movement of Loads

2. Condition of Rigging and Hoisting Equipment

3. Weight of other equipment apart from hoisting equipment

4. Inexperience of Operators

Javed Hussain
من قبل Javed Hussain , Sr.EH&S Executive , Aisha Steel Mills

The factors could considered in rigging are: Competent rigger, work permit system, method statement, Emergency procedure, Proper inspection of rigging tools that is, Slings, Wire, Shackles, Load chart of crane should be according to weight, proper inspection of area soil condition, and the control measures related falling and collapse hazards, and also 

Menhadenn Sumaya
من قبل Menhadenn Sumaya , Rigger 3 , Charge Hand , JGC Sub. CCC Consolidated Construction Company

Speaking about factors in rigging, first thing to do is safety and check your area before lifting but most of all is initiative, do things without being told. 

jan vincent kasayan
من قبل jan vincent kasayan , FOREMAN RIGGING , QCON ENGINEERING and CONSTRUCTION

1.know the weight

2.know the capacity

3.retain the load

4.control the load

Bill de Beer
من قبل Bill de Beer , Superintendent , Nico Klopper (0836312802)

the risk assessment, What does the load way, the radius of the load, the ground stability, access to the area, crane certification and inspections, crane driver competency, lifting equipment inspections, crane capability, rigging study, supervision ect.

Jodi waddell
من قبل Jodi waddell , Rigging Foreman , various offhshore companies

1. S.W.L - Safe working load of equipment

2. W.L.L - Working load limit.

3. Weight of load to be moved.

4. Method of lifting load, along with special awareness of pick up and laydown area.

المزيد من الأسئلة المماثلة