ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

In Project Management, Phase exits, kill points and stage gates are used for what purpose?

user-image
تم إضافة السؤال من قبل Abdul Rehman Zaheer , Marketing & Projects Specialist , King Fahd University of Petroleum & Minerals
تاريخ النشر: 2014/03/17
Abdul Samad Nadeem Malik
من قبل Abdul Samad Nadeem Malik , Business Support Officer , Thimar Al Jazirah - 3M ESPE

The conclusion of a prject phase is generally marked by a review of both key deliverable s and project performance to date, to a)determine if the project should continue into its next phase and b)detect and correct errors cost effectively. these phase-end reviews are often called Phase Exit, Stage Gates, or kill points.

المزيد من الأسئلة المماثلة