So many in30+ years of my professional career.
The reasion has always been one of these
Differing a project is mainly on two consideration. One is lack of fund and the other is external or environmental forces difficult to overcome. Hi ever prioritising of project is on financial criteria like IRR, payback period etc.An activity in a project can be postponed if it not fall on the critical path and depending on the slack of that activity in the parallel path.
1. Due to decision of line managers/decision making authorities
2. Extremism and political conflicts in working area, government decisions or some emergency situation
one is inventory, i had to postponed the purchase of stocks due to insufficient fund.