Cost and Variance Measures:

The purpose of a flexible budget is to: a. provide management with slack in their budget. b eliminate fluctuations in production reports. c. compare actual and budgeted results at various levels of activity. d. make the annual budget process more efficient.

user-image
تم إضافة السؤال من قبل Anayatullah Tahir , Accounting Consultant , Various
تاريخ النشر: 2014/03/24
Rashad Moursi
من قبل Rashad Moursi , Financial and Administrative Officer & international Business Transformer, Hotel Owner Reprs. , Investment and financial

C. compare actual and budgeted results at various levels of activity.

Shafiulla Mohammad
من قبل Shafiulla Mohammad , Customer Service Adviser , University of Bedfordshire

The answer is option C.

 

Muhammad Zubair
من قبل Muhammad Zubair , CFO / Chief Accountant , RH Group

Correct answer is c