أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. The risk register contains the results of qualitative risk analysis, quantitative risk analysis, and risk response planning B. The risk register is a component of the project management plan C. The lowest level of the RBS can be used as the risk register
Risk Register is not component of Project Management Plan, it is independent document contain a list for all identified risk on the project and their characteristics
(So B is false)
The result of qualitative risk analysis and quantitative risk analysis is probability, impact and expected value and proximity and all of those must be in risk register document also risk response categories and risk response actions must be in the risk register document
(So A true)
The lowest level of the RBS can be used as the risk register but it the main benefit for the RBS to describe the risk categories
(So I will consider C true)
Very thanks, it is good question:
A is false.
B and C are true
C will be the false option
Its Answer is ......C. Only C.
Same answer of Mr Raafatsallam
Every one have his own visions
i beleive( c) is false
RBS can not ne used as risk register, so the answer is c
I think the logical answer should be 'C'.
هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟