Below mention quantities my own calculation in my current project.

 

 

Column and Roof Beams 181.42 kg/m3 Roof Slabs (240mm thick) 158.9 kg/m3 Small Bases (below3m3) 89.06 kg/m3 Grade Beams 206.94 kg/m3 Medium Bases (between10-20m3) 144.03 kg/m3 Retaining Wall 69.25 kg/m3 Ground Floor Slab (240mm thick) 67.09 kg/m3 Area Paving (100mm thick) 69.65 kg/m3 Duct Bank 59.76 kg/m3 Sleeper Pedestals 71.62 kg/m3 Building Walls (300mm thick) 157.63 kg/m3

Salauddin Syed
من قبل Salauddin Syed , Cost Manager , Currie and Brown consultants

if u r talking about density of steel then it is7850 kg/m3 and weight of reinforcement over concrete changes as per design and it varies according to type of constuction.

 

 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Dear Habeeb, It is depend how much MPA for the concrete, higher concrete MPA need high rebar also. As my experience for Fc32 is200 -250 kg/m3. For Fc40 is200 -400 kg/m3, but these are not efficience. Normally the ideal is110-125 kg/m3. I hope this information useful for you. Thanks Andi

Selva Dass
من قبل Selva Dass

Hi., Actually what is your % steel by volume of Concrete.. Please tell me sir.

Tanveer Ahmed
من قبل Tanveer Ahmed , Civil Estimator/Quantity Surveyor , Shade Corporation Ltd.

Approximately the Ratio of Steel for Beams is 160 kg/m3

JAVED YAQOOB JAVED
من قبل JAVED YAQOOB JAVED , Sr.Quantity Surveyor , Dar Al Handasah (Shair and Partners)

reinforcement weight is 7850kg/m3

Alex Salinas
من قبل Alex Salinas , Project Quantity Surveyor , PMQS Solutions Construction, Inc.

common weight of reinforcement is 150 kg/m3.

Karthikeyan Sekar
من قبل Karthikeyan Sekar , Quantity surveyor , EMCO QATAR

Footing - 80 kg/cumeccolumn - 160 kg/ cumecBeam - 110 kg/ cumecslab - 80 kg / cumec

jay raj bista
من قبل jay raj bista , Civil Engineer , Abdulla Nass Group

average 120 kg/m3 in beam and slab

sajid Mumtaz Raza
من قبل sajid Mumtaz Raza , Project Architect , Ford Motor Company

Bases Beams Capping beams Columns Ground beams Footings Pile Caps Plate slabs Rafts Retaining walls Ribbed floor slabs Slabs – one way Slabs – two way Stairs Tie beams Transfer slabs Walls – normal Walls – wind NOTE: For exposed elements add the following:Beams +100%; Columns +15%; Walls +50%Average values for typical concrete frames:Heavy industrial = 130 kg/m3Commercial = 100 kg/m3Institutional = 90 kg/m3 90-130250-350 135 200-450 230-330 70-100 110-150 95-135 115 110-150 80-120 75-125 67-135 130-170 130-170 150 70-100 90-150 

jaberkhan pathan
من قبل jaberkhan pathan , Quantity Surveyor,Estimator , Srujan Construction Management Solutions

Originally it is depends on the design..it may be vary 105 kg/cum to 160 kg/cum.It will be less for Plinth beam as compared to floor beam.