Which of the following statements are FALSE regarding the project scope management plan?

A. The project scope management plan describes how the project scope will be defined and managed by the project scope management team B. The project scope management plan specifies how formal verification and acceptance of the project deliverables will be satisfied. C. The project scope management plan is contained within the project management plan. D. The project scope management plan identifies the influence and interest of the stakeholders and documents their expectations E. The project scope management plan is an output of the Scope Planning process

user-image
تم إضافة السؤال من قبل Mohamed El Sayed , Project Manager , Saudi Post
تاريخ النشر: 2014/05/19
مستخدم محذوف‎
من قبل مستخدم محذوف‎

I am a supporter of hydration for28 days with ambient air protection coverage if possible

Salauddin Mohammad
من قبل Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

D

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer D is the best one

 

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

D. The project scope management plan identifies the influence and interest of the stakeholders and documents their expectations.

Tanveer Qureshi
من قبل Tanveer Qureshi , Director , Qureshi Associates

D is appropriate answer.