أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Project scope B. Organizational project assets C. Preliminary project scope statement D. Approved change requests E. Scope baseline
The project document is used to update the manual of the third edition of the Project Manual, which summarizes the processes, inputs and outputs that are often considered ...... and the integration and articulation of the project, the important integration procedures to complete the project, A work is a narrative of the products or services that will result from the project ...... This baseline includes all approved budgets except reserves
Approved change requests
Organizational project assets
D is the best response. The project scope management plan includes preparation of a detailed project scope statement, creation of the WBS, and a process specifying how formal verification and acceptance of the completed project deliverables will be obtained. 2.Answer A is correct. A properly sized work package is one that is small enough to allow for reliable estimates for required resources and duration. Answers B, C, and D are incorrect because they assume that you are working toward some artificial target that does not contribute to appropriately sized work packages. 3.Answer A is correct. The project charter is one of two defined inputs for the collect requirements process. (The other input is the stakeholder register.) Answer B is incorrect because the requirements traceability matrix is an output for the collect requirements process. Answers C and D are incorrect because they refer to inputs from other processes.