Bayt.com Specialities

Expand your network. Exchange professional knowledge.
Demonstrate your expertise.

muhammad-farooq-4071441
Question added by Muhammad Farooq, QA-QC Manager, AL Bawani Contracting Co - 8 years ago

Earned value = 650, planned value = 550, actual cost = 700. What is the SV at this point in time? a. + 100 , b. – 50, c. – 100, d. – 150 ?

ERP

Cost Management

Earned Value Management

Project Management

Answers:
4
Followers:
3
Views:
10
Vote Count:
0

Log In

Don't have an account? Register here


OR

Bayt.com never shares any of your activities through Facebook or Google without your explicit permission.