The best approach is to disconnect all distribution network loads before returning the power on the main Breaker. Then start connecting loads one by one till find the defected branch. At that time the fault will occur again and you've to disconnect the faulted branch to repair it is fault.

adeniji david adebisi
by adeniji david adebisi , team lead technical operation , POWER HOLDING COMPANY OF NIGERIA

firstly deload the whole circuit, then start loading them back , one by one  with testing lamp in order to avoid short circuit

MOHAMED ELMELEGY
by MOHAMED ELMELEGY , instrument engineer , Segas LNG plant

totally i agree with eng Yehia 

 

this the best way to solve in a short time 