Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

If an approved shop drawing for installation of a MEP service contradicts the Project Specification, which one you will follow ?

user-image
Question added by Anjum Jamal , QA QC Engineer , Khatib & Alami
Date Posted: 2014/07/31
hameed kadher mustafa
by hameed kadher mustafa , MEP Project Manager , Hill International

Slight modifications are acceptable if required as per site conditions.

But whatever changes eventhough minor should be notified /brought to the knowledge of consultants

Deleted user
by Deleted user

Project Specification will be govern it is a reference guide for the implementation, execution of works during construction at sites. If any, in case that the approved shop drawing contradicts with the specifications, the issue must be raised to management/client to discuss and make a possible action.

 

 

Gener Mercurio
by Gener Mercurio , Senior Qaqc Engineer , plafond fit-out company

The question is wrong. How on earth would a shop drawing be approved when it is contradicting an specified project specification? And where can you find an MEP contractor who will prepare a shop drawing that will not follow or contradict the specification, and hoping to be approve by the consultant? If in some way this thing happened, then its either the consultant doesnt know the specification and just blindly approving the shop drawing. Or, the consultant who approved the shop drawing is highly incompetent. Normally, a shop drawing is prepared base on the IFC or Issued for Construction Drawings given by the consultant/client designer. This is so that it is very unlikely that the designer of the shop drawing will deviate from IFC without raising RFI if needed.

Saad Al Deen Hashem
by Saad Al Deen Hashem , Architect / Technical Coordinator , Generic Engineering Technologies (GET)

Every projects is binded with its own Constitution that the contractor have to follow and execute with but as every law in the world most of the times there are conditions (availability of the materials, site conditions, trasnportation of materials,...etc) that oblige changes in the preminarally spicifications and the consultant will issue new clauses according to these conditions that are reflected in the approved shop drawings and side notes. So my answer will e Approved Shop Drawings.

Anub Pillai
by Anub Pillai , Senior MEP Project Manager , BIC Contracting LLC (Previously known as Habtoor Leighton Group

If you comapair shop drawings & Project specification then specification always have precedence in Project.

Ismail mydeen Abdul rahman
by Ismail mydeen Abdul rahman , QA/QC Engineer - MEP , International Electromechanical Service Co. (IEMSC)

Specification to be followed

Chakra Dhar
by Chakra Dhar , Senior Mechanical Engineer , ARENCO Consultants

Project specification.

syed khan
by syed khan , Project Engineer - Mechanical , Voltas Limited

specification

Ronnel Domingo
by Ronnel Domingo , Project Electrical Engineer , Target Engineering Construction Co.

The Project Specification shall be followed because it is the specified requirement of the project. If there is a deviation from the Project Specification, proper TQ shall be raised followed by CR for the approval of the said deviation.

Waled Elwan
by Waled Elwan , Marketing Engineer , Sumitomo Corporation

Project spesifications are ruling the execution and that is the  standard practice according to the contract signed between the2 entities. However in some cases an erupted need which require a change that has to be approved by both the consultant & the owner  upon presenting the shop drawing & documents that justifies the change  to the consultant to be approved first  before the execution.

Aldous Winifredo Buniel
by Aldous Winifredo Buniel , MEP Electrical Engineer , Built Contracting Company

Specification of project is guidance of Execution and implementation base on engineering standard practice. Some condition need to be modified depend on the site condition and practical due to a valid reason and notes upon presenting the approved shop drawing to consultant before the execution.

More Questions Like This