What is the quantity of cement required for 100 sq.m cement concrete (1:2:4) 4 cm thick floor?

user-image
Question added by Mubeen Ali PK , Assistant Engineer , PMGSY (Pradhan Mantri Gram Sadak Yojna) - Rural Road Development Authority- Govt. of India
Date Posted: 2014/08/05
Deleted user
by Deleted user

Thickness =4cm=0.04m

Volume of wet concrete is1.54 to1.57

Ratio of mix1:2:4

Volume=1+2+4=7

unit weight of cement bag is1440 kg/cum one bag of cement =50/1440 =0.034722 cum

Quantity of cement = (1/7)=0.1429*1.54=0.22

                                        =0.22/0.0347

                                       =6.34bags

Weight of1 cement bag=50kg

                                         =6.34*50

                                        =317kg of cement is required

 

جعفر هندي زين السقاف
by جعفر هندي زين السقاف , "Certified trainer by the Yemeni Engineers Syndicate." , Engineers Syndicate

0.571cu.m of cement , approximately28 bags(50kg)

Umar Lebbe Sitheeq Lebbe
by Umar Lebbe Sitheeq Lebbe , Site Manager/Planner , JFE Engineering Corporation - Japan

for one cubic meter concrete needs6-7 bags of cement (50kg)

ibrar khattak
by ibrar khattak , site engineer , faizan-e-madina

Cement required for100sqm work =0.87 cubic meter25 bags

Matt Manalac
by Matt Manalac , Senior Site Engineer , WSP Middle Eas

40 bags.

Nelio Beleo
by Nelio Beleo , Civil Inspector , Petrojet

It is approximately 25 bags of 50 kg cement for a total of 4 cubic meter concrete.

shazaib khan
by shazaib khan , Assistant Manager/ Senior Executive - MIS , Sanskriti Enterprises

21.11 bags

Azhar Bashir
by Azhar Bashir , Senior QA-QC Engineer , Al Arif Contracting Co

Approximately25 Bags of50 Kg cement with a dry cement volume of0.88 cu.m

nader mohammed
by nader mohammed , Director Manager , al jaber group-Saudi Arabia

Thickness4 cm Q=4m3 and for line concrete200kg per m3 the total800 kg

Syed Mohamed Ibrahim
by Syed Mohamed Ibrahim , Site Engineer , JBK Controls

cement required for100 sq.m =6bag 