It probably depends from project to project but most of the answers already given are accurate.
TERMITE PROTECTION IS APPLIED IN THE FOUNDATION FILLING
Termite protection is applied after excavation the foundation and before starting of foundation
before foundation work( after earth work excavation)
TERMITE PROTECTION SHOULD APPLY AFTER THE EXCAVATION WORK AND BEFORE THE CASTING OF FOUNDATION
1), Just when excavation is completed.2) before backfilling the sides of the foundation3) during wood work
In the start of construction
termite protection is applied when the structure is in its foundation level .
But what is the use of applying this protection before the lean concrete or backfilling ?! isn't it enough to apply it, as Shaik Abdul Khaja Moinuddin comment, before construction of grade slab?! This will protect the structure from termite not to reach the floor ?! what do you think?!
Shaik Abdul Khaja Moinuddin Projects Planner at Nabil & partners
Follow
Termite protection is used in preparation for the construction of the foundation. It is applied over the soil bed, right before you cast the blinding concrete. The construction sequence of the raft is excavation -> termite control -> blinding concrete -> waterprooding -> screed -> raft.