Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During scaffolding for maintaining a roof of steel plant what will be considered for Risk assessment?

While production is in progress

user-image
Question added by AMIR UDDIN ANSARI AAMIR , EXECUTIVE , TARAPORE AND COMPANY
Date Posted: 2014/08/12
alliver revilla
by alliver revilla , Scaffolding/Firewatcher , CAPE

When planning for risk assessment you must considered everything that can cause harm to persons or can damage to plant,equipment,materials.

Five steps to risk assessment can be followed to ensure that your risk assessment is carried out correctly, these five steps are:

                ·         Identify the hazards

·         Decide who might be harmed and how

·         Evaluate the risks and decide on control measures

·         Record your findings and implement them

                ·         Review your assessment and update if necessary

Samran Jamil Qazi
by Samran Jamil Qazi , Director Operations , Mender Engineering (PVT) Limited

Project supervisors, designers and contractors have legal obligations in relation to risk assessment and each should seek to avoid risks.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.