You are a project manager for an agricultural supply company. You have interviewed stakeholders and gathered requirements.

Which of the following is true regarding the process this question refers to? A. The requirements document lists the requirements and describes how they will be analyzed, documented, and managed throughout the project. B. Requirements documentation consist of formal, complex documents that include elements such as the business need of the project, functional requirements, nonfunctional requirements, impacts to others inside and outside the organization, and requirements assumptions and constraints. C. The requirements documentation details the work required to create the deliverables of the project, including deliverables description, product acceptance criteria, exclusions from requirements, and requirements assumptions and constraints. D. The requirements traceability matrix ties requirements to project objectives, business needs, WBS deliverables, product design, test strategies, and high‐level requirements and traces them through to project completion.

user-image
Question added by Sawla Varouqa , PCS Manager & MEL Officer for USAID/Jordan Water Engineering Services (WES) 10 M USD. , SAJDI – Consulting Engineering Center (CEC).
Date Posted: 2014/08/26
Alok Gupta
by Alok Gupta , SAP Practice Head , Rungta Mines Limited

C

Sumit Gupta
by Sumit Gupta , Joint Director , Indian Navy

Option B

حسام السداتى
by حسام السداتى , مدير تسويق , أكاديمية السادات للعلوم الإدارية

C. The requirements documentation details the work required to create the deliverables of the project, including deliverables description, product acceptance criteria, exclusions from requirements, and requirements assumptions and constraints. 

Salauddin Mohammad
by Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

C

Tano Paiva
by Tano Paiva , Logistics Manager, , V2 Aerospace FZE

C

AmanUllah PMP®
by AmanUllah PMP® , Project Engineer , Technical and Industrial Services Co.

C

hossam azzam
by hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

C

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
by VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

D. The requirements traceability matrix ties requirements to project objectives, business needs, WBS deliverables, product design, test strategies, and high‐level requirements and traces them through to project completion.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

I think option c is applicable.

GAVIN BENN
by GAVIN BENN , Senior Project Manager , Palmera/ UCC

Option B is my choice -. The information  gathered from stskeholders both inside and outside the organization is  imperative and critical to the PM team in developing the project scope statement. Options A, C, and D focuses more on information requirements- from stakeholders more directly related to the project. such as the sponsor(s) and project team. Option B on the other hand would include information from stakeholders directly and indirectly related to the proect such as persons or groups opposing the project, regulations agencies etc.  - All stakeholders.

Ahmed Muhammad El-Sayed Bassiouny
by Ahmed Muhammad El-Sayed Bassiouny , Customer Care Supervisor , Noon.com

[ B ]