Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

For how much time brick should be soaked in water before laying?

user-image
Question added by Muhammad Khalil , Chief Engineer (Civil) , Water and Sanitation Services Mardan
Date Posted: 2014/09/10
Muhammad EL Faham PMP®
by Muhammad EL Faham PMP® , Construction Manager , Arabtec Construction LLC

Bricks should be soaked in water before use for a period that is sufficient for the water to just penetrate the entire depth of bricks. The period of soaking is generally at least six hours. The period of soaking can be determined by a simple field test at site.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.