to cut things short you should mainly consider the following :
1-Cable grouping factor (how many cables in the same duct and the heat they produce due to the passing current )
2-the duct filling percentage to allow the cables to be pulled ,
3-the different service levels ( a cable carrying high current shouldn't be passing in the same duct or on the same cable tray level with a cable carrying instrumentation signals or a control cable to avoid induction of currents that could lead to major problems .