How to track performance % progress when the schedule is not resource loaded?

user-image
Question added by Anirwan Sengupta , Manager - Planning & Contracts , Sendan International Company Limited
Date Posted: 2014/10/21
MOHAMED IMRAN
by MOHAMED IMRAN , Planning and Scheduling Engineer , ARABIAN GULF CONSTRUCTION

Performance % Complete can be tracked by Duration % Complete or Quantity (Physical) % Complete if schedule is not resource loaded.But anyhow cost is needed to calculate Performance % Complete at WBS level.