How the line Manager of process plant react during plant outages due to human negligence?

user-image
Question added by Arvind Srinivasa Venkateswara Rao Devulapalli , Consultant-Process -Commissioning , Toyo Engineering India Ltd
Date Posted: 2014/10/28
Rashid Waseem
by Rashid Waseem , Manager Projects , EI Controls/En-Solar

1. Looking for critical plant zones to be well in place after outage.

2. Reinstate first those areas which are critical.

3. Recall best staff for emergency.

4. Personally help your staff.

5. Inquiry of incident and fixation of responsibility.

Mohammed AlMadani
by Mohammed AlMadani , senior Operator , barrick mining LTD

he should be calm and try to start plant as fast as they can .

after that make investigation and improve the staff work by training  