If a resource required by the project is under deadlock condition, what will be your strategy to solve the issue ?

user-image
Question added by Muhammad Usman Tariq , Visiting Faculty , National University of Science and Technology
Date Posted: 2014/10/29
Sasa Stavric
by Sasa Stavric , Engineer Techinician , Kombinat

find the problem,and then take steps to achieve fast setting

Abdulgafar Mohammed
by Abdulgafar Mohammed , Project Manager/Fire Inspector , Chronicle International

If the resource is critical, then we might need to have a meeting with the client. If it is a human resource situation, i would suggest out-sourcing. If it is a material resource or any other, then we might have to adjust the schedule and other elements accordingly.

sajid m s
by sajid m s , PROJECT ENGINEER , Inmarco FZC

Check whether this deadlock condition resource is critical in the project. If yes, and it cannot be recovered from the current status without irrecoverable losses, entrust the succession resource on the job immediately.Else, take it easy, manage with other resources, taking care not to over allocate or scheduling them.