Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The labour rate variance can be calculated by the following equation:

a. Budgeted labour costs - actual labour costs b. (Standard wage rate - actual wage rate) * standard hours worked c. (Standard hours - actual hours) * actual wage rate d. (Standard wage rate - actual wage rate) * actual hours worked

user-image
Question added by Vinod Jetley , Assistant General Manager , State Bank of India
Date Posted: 2014/10/31
Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

b. (Standard wage rate - actual wage rate) * standard hours worked