Provide the team with enough information to properly estimate each activity.
Let those doing the estimating know how refined their estimates must be.
Complete a sanity check of the estimates.
Prevent padding-adding more time and cost to estimation when no information available )
In addition to the answer above . Project manager ensures that any assumptions created during estimating should be recorded for review . Project manager formulates reserves.