(Changing the requirements and/or specifications) represents what kind of risk management response strategies:

<p>1. sharing.</p> <p>2. diversification.</p> <p>3. avoiding.</p> <p> </p> <p> </p> <p> </p> <p> </p>

user-image
Question added by Almutaz Bakry Sidahmed , Internal Audit Manager , Banan real estate
Date Posted: 2014/11/22
Ahmed Eldow
by Ahmed Eldow , Internal Auditor , Petroline for Crude Oil

transfer risk, accept risk, avoid risk and reduce risk

Bilal Naeem
by Bilal Naeem , Assistant Manager Assurance , RSM Bahrain

Given the limited information  - I think it could be either avoiding or diversification depending on the nature of the change. I would however suggest the "mitigate (not in the list)" response as it fits the situation better than the three.