To expedite the completion of a villa construction; what would be the appropriate solution to ease the Project Manager's request of completion?

user-image
Question added by Mansueto Gallego , Project Planner , Consolidated Construction Company-SCHEMA Management
Date Posted: 2014/11/30
Zia Rehman
by Zia Rehman , Director Project Management , M/s U.C.C Private Limited

Following steps could be taken.

  • Prepare a Critical Path Method diagram, if not already in place. Analyze it and see as to how we could resort to project crashing, if possible.
  • Evaluate the analysis keeping in view budget, resources availability, etc..
  • If budget allows and project crashing is viable, prepare the plan.
  • Manage the resources, implement the plan, monitor & control the activities, review the plan as may be necessary and;
  • Celebrate the Completion of project on completion.  