Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Activity,in critical path is delayed.What should you do? 1)Compress Schedule 2)Scope Out 3)Inform Cust. about delay 4)Deliver Uncompleted activity

user-image
Question added by RAJ DAHIYA , Project Manager - Energy Optimization , Siemens
Date Posted: 2014/12/17
Ibrahim Hussein Mayaleh
by Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

If any delay to any of the activities on the critical path occurs, the whole project will be delayed unless the company takes action and makes other changes to bring the project back on track. The company can choose to compress schedule and avail additional resources if necessary without the need to inform the customer.

However, in huge projects, customers usually assign a representative to be part of the project management team which allow them to be aware of progress.

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is (3) Inform the Customer about the delay.

LABIB KOOLI
by LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

I guess you should try at first with option1. Compress schedule 

then option2.Inform customer if the delay still remaining.

 

 

If there is a delay in any of the activities under the critical path, there will be a delay of the project deliverables.

Most of the times, if such delay is occurred, project acceleration or re-sequencing is done in order to achieve the deadlines.

A critical path diagram should be constantly updated with actual information when the project progresses in order to refine the activity length/project duration predictions.

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Always inform the customer, but first see what you can do with the schedule, so you can inform the customer , because he will ask you what can be done about it!

Naeem Tariq
by Naeem Tariq , Events Coordinator , Elite Valet Parking Services

Inform Cust. about delay is the best step

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

3)Inform Cust. about delay

Mohammed Abdul Hannan
by Mohammed Abdul Hannan , Planning Manager , North 25 (Subsidary of Dubai Holding & Meraas)

The first thing is to inform about the delay and secondly try to compress the schedule

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
by VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

First option could be >>>> Compress the Schedule

(May also be resorted to inform the customer, if there is no confidence in the compressed schedule)

Amr Mohamed Mahmoud Youness Youness
by Amr Mohamed Mahmoud Youness Youness , موقع و اداره مشروعات , With Free Contractor

Inform the customer about Delay

Mohammed Imad ullah
by Mohammed Imad ullah , Risk Investigator , Amazon Development Centre

The best way to slove this problem is to compress the schedule and add some resources if possible inspite of this if the work is not back on track then comes the reputation its better to inform the customer if thers no representative of his in your firm ..... but have to put efforts to get back on track n informing should be the last option

Option3) Inform Cust. about delay

This option should be taken as an immediate first step to follow compare with other options.

More Questions Like This