When the project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

<p><strong>A. Performance management</strong><strong>B. Scope identification</strong><strong>C. Risk identification</strong><strong>D. Project team status meeting</strong></p>

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/03
Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

my choice is Answer:   C) Risk identification 

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer C: Risk Identification, past experiences are very important  like mr. Tariq stated

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes, the correct answer is C. Risk identification.

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

Risk identification

Deleted user
by Deleted user

Thanks Mr. Alex

Agreed with the masses 

LABIB KOOLI
by LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

Definitely C.Risk identification 

Muhammad Usman Tariq
by Muhammad Usman Tariq , Visiting Faculty , National University of Science and Technology

Risk identification is the priority before starting of the project. Past lessons serve good.

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
by VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Answer option (b) >>>>>>>>>>>>>   Scope Identification.

How the previous experience can be made use of in the current circumstances.

Bashar Jadallah
by Bashar Jadallah , Senior Architect, Project Manager , Dar AlOmran

a. performance management

Deleted user
by Deleted user

I think it is more of performance management than risk identification.

 Risk identification will be covered in performance management anyway, I think.