The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project.

<p><strong>Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?</strong><strong>A. Change control system</strong><strong>B. Process analysis</strong><strong>C. Benchmarking</strong><strong>D. Configuration management system</strong></p>

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/03
Mohamed Galal Hussein Ahmed Mohamed
by Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

My answer is "B": Process analysis

My choice is answer "A" Change Control System 

RAJ DAHIYA
by RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

B. Process analysis, is the correct answer

Deleted user
by Deleted user

I am little confused, and my answer is none of the above.  (which is not the option)

Change control system is to document change, may also address output of process. I think this is the closest one.

If I am allowed to add option there, I would say;

Either process validation or post implementation survey.

Irina Chepel
by Irina Chepel , Personal trainer , Freelancer

Process analysis, but I'd say that partly all techniques are important

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

The Process Improvement Plan documents the steps for analyzing processes with the purpose of improving the process. You should consider things such as process boundaries, process configuration, process metrics and targets for improved performance. 

LABIB KOOLI
by LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

I guess A. Change control system

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

B. Process analysis.

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer D, but answer C benchmarking is also a tool but harder to use during a Project, because the specific project details make benchmarking hard, but for certain processes possible

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

 I agree the optopn C

Benchmarking:

 

Robert Sibanda
by Robert Sibanda , Head of Department , Rosettenville Central School

B Process Analysis  with checks and balances while the project is in process