You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only

<p> after two days of completion of painting of walls. This is an example of</p> <p>a.Lag b.Lead c.Slack d.Float</p>

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/07
Deleted user
by Deleted user

Hi...

This is an example of lag...

kevil Vavaiya
by kevil Vavaiya , Civil Engineer , ASCO Consulting Engineers

Answer is A) Lag

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

A: Lag is the amount of time after the completion of the predecessor activity, when the successor activity can start.

Deleted user
by Deleted user

Lagging

mohamed shaaban ramadan moursi moursi
by mohamed shaaban ramadan moursi moursi , project manager , PEAKS CONSTRACUTIONS & MAINTANANCE COMPANY

a.) Lag

Dejan Petrovic
by Dejan Petrovic , Director , virtualarchitecture d.o.o.

a. Lag

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

a. Lag

Elias Gaouro
by Elias Gaouro , Business Analyst, Supply Management , Airbus

A

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

my choice is a) Lag