<p>A. The work package codes</p> <p>B. The project identifiers</p> <p>C. The code of accounts</p> <p>D. The element accounts</p>
C
Code of accounts, so answer C
The answer is :
C. The code of accounts
C. The code of accounts
Based what I have found my answer is A. The work package codes
Each item in the WBS is generally assigned a unique identifier; these identifiers can provide a structure for a hierarchical summation of costs and resources. The items at the lowest level of the WBS may be referred to as work packages, especially in organizations that follow earned value management practices. These work packages may in turn be further decomposed in a sub-project work breakdown structure. Names for work breakdown structure levels:
It should be the code of accounts (C)
Code of Accounts. - this is a project management tool which assigns a code made from numbers, letters or a combination of the two to every item on the WBS of a project.
.