Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

If actual cost (AC) = 500, planned value (PV) = 600, earned value (EV) = 700 what is cost variance (CV)?

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/13
RAJ DAHIYA
by RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

200

CV = EV-AC

Irina Chepel
by Irina Chepel , Personal trainer , Freelancer

200 of course

Hany Ahmed Omar
by Hany Ahmed Omar , Project Engineer , Etihad Contracting Company

CV = EV - AC

CV =700 -500 =200

 

Basit Ali
by Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

CV200

Deleted user
by Deleted user

Vow, everyone is right on the money.

Jahabar Sadiq Ifthikar
by Jahabar Sadiq Ifthikar , Procurement Manager , Compass PMC

The answer

CV = EV - AC

200 =700 -500

I Agreed Mr.Alex Al Yazouri  

CV = EV - AC =700 -500 =200

SV = EV - PV =700 -600 =100

So the project is under budget and a head of schedule

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

see above, only need to know that CV = EV-AC

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

 cost variance =  earned value  -  actual cost

        CV            =          EV           -        AC 

        200           =         700          -        500             

Muhammad Shakeel
by Muhammad Shakeel , CAD Design Manager , M/S zeeruk Intl.

CV = EV - AV    (700-500=200)

Cost Variance =200 

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

I agree... if the actual cost is500 and the earned value is700 the difference/cost variance is 200

 

More Questions Like This