Register now or log in to join your professional community.
A. Create a contingency plan B. Create a risk management plan C. Create a WBS D. Create a scope statement
As a project Manager to ensure that all job is included in the project I should assert that there is a fair repartition of tasks among the group. Every person should handle a special criteria to ensure that all are participated in job . the right person in the right place and every one through his productivity and experience. This is how the circulation of work should be .
Option C
C. Create a WBS
is the correct answer.
It is called answer D A scope statement or scope management plan
Option C : Create W.B.S.
The best answer is C.
Create Work Breakdown Structure
The best way is to creat a WBS, option C.
(c) Create a WBS that groups project components that defines the whole project scope