A.Resource levelingB.Resource planningC.Cost estimatingD.Cost budgetingE.Cost control
A.Resource leveling
AS
There are4 processes in this knowledge area including
A. Resource leveling
Resource leveling is the part of the scheduling process in which the start and end dates of tasks are driven by resource limitations,
Such as limited availability of resources or hard to manage resource levels.
the answer is A; but my opinion is that the are indirectly included
A
A + E = Project Cost Management
I agree with Alex
A.Resource leveling,
I believe Resource Leveling (A) as it is a method to adjust the start and the end of the project depending on the resource constraints
Option A.
Resource leveling
Agreed with experts
Option "A"
I would go for option A.