In the context of estimation, a heuristic is best described as a: a) control tool. b) scheduling method. c) planning tool. d) rule of thumb.

user-image
Question added by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill
Date Posted: 2015/01/21
Nelio Beleo
by Nelio Beleo , Civil Inspector , Petrojet

The answer is D) rule of thumb

hamid bezzout
by hamid bezzout , Maintenance engineer , OBY Maroc Sarl

c) ==========> planning tools

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

d) >>>>>>>> rule of thumb.

Christopher Habib
by Christopher Habib , Pre-Sales Engineer (Project Solutions Officer) , Mitsulift And Equipment Sal

d) Rule of Thumb