If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV)? a) 350 b) -75 c) 400 d) -50

user-image
Question added by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill
Date Posted: 2015/01/21
Mohideen Siraj
by Mohideen Siraj , Business Development Manager , Prompt Trade Fair Services Pvt Ltd

 Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC).

Hence it proved D) -50

Mustansar Jamil
by Mustansar Jamil , Senior Planning Engineer , Chiyoda CCC Engineering Ltd.

CV = EV - AC =350  - 400  =  -50

Erman Farizal Daud
by Erman Farizal Daud , Operation Supervisor , Nautic Offshore Pte. Ltd.

d) EV-AC (350-400) = -50..if im not mistaken

Muhammad samran
by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

thanks all gave the right answer.

Oladipupo Elesha
by Oladipupo Elesha , Executive Officer , ARM Pension Manager PFA Ltd

CV = EV - AC =350  - 400  =  -50

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

d) -50

CV = EV - AC =350  - 400  =  -50

 

Christopher Habib
by Christopher Habib , Pre-Sales Engineer (Project Solutions Officer) , Mitsulift And Equipment Sal

D) -50 since CV = EV - AC