Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC).
Hence it proved D) -50
CV = EV - AC =350 - 400 = -50
d) EV-AC (350-400) = -50..if im not mistaken
thanks all gave the right answer.
CV = EV - AC =350 - 400 = -50
d) -50
CV = EV - AC =350 - 400 = -50
D) -50 since CV = EV - AC