by
Homam Khawajki , Solution Architect / Professional Engineer O&M , Batelco
- Knowledge Areas Become10 (it was9)
The additional one is Stakeholder Management.
- Additional5 Processes, so they become47 as total (42 Processes were in4th Edition)
The new processes are:
Plan Scope Management
Plan Schedule Management
Plan Cost Management
Plan Stakeholder Management
Control Stakeholder Engagement
-The following two Processes:
Identify Stakeholders
and
Manage Stakeholder Expectations
Are moved From
Project Communication Management
to
Project Stakeholder Management