I. Measurement of performance.II. Comparison of actual and standard.III. Analysis of causes of deviation.IV. Actual performance.V. Corrective action plan.
(a) (III), (IV), (V), (I), (II) (b) (II), (III), (IV), (V), (I)(c) (I), (II), (IV), (III), (V) (d) (IV), (I), (II), (III), (V)(e) (V), (IV), (III), (II), (I).
Option- D
IV). Actual performance
I). Measurement of performance
II). Comparison of actual and standard.
III). Analysis of causes of deviation
V). Corrective action plan
its41235, answer is D.................
Good question, thank you.
(d) >>>>>>>>>>>>>(IV), (I), (II), (III), (V)
IV. Actual performance
I. Measurement of performance
II. Comparison of actual and standard.
III. Analysis of causes of deviation
V. Corrective action plan
I fully agree with you MR Vinod jetley.
thanks.
(d) (IV), (I), (II), (III),
(d) (IV), (I), (II), (III), (V)
(d) (IV), (I), (II), (III), (V) ............. . . . .