As compared to ordinary portland cement, high alumina cement has:-

a) higher initial setting time but lower final setting timeb) lower initial setting time but higher final setting timec) higher initial and final setting timesd) lower initial and final setting times

user-image
Question added by Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.
Date Posted: 2015/02/25
محمد يونس
by محمد يونس , مهندس مشرف , الشركة العامة للكهرباء

this  type the initial setting time  by BS915-2:1972 (1983) as between2 and6 hours typical values for this type are initial set at2,1/2  hours and final set at30 minutes therefore slow setting but final set follows the initial set more rapidly then is the case in Portland cement. i choice  b) lower initial setting time but higher final setting time

Mohamd Sltan
by Mohamd Sltan , Volunteering, Business Development, Freelancing, Training , Running Own Business and Managing Community Association

Answer is A.  This type of cement is slow-setting. The initial setting time is2 to6 hours although final setting takes place approximately2 hours after initial set.

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

High alumina cement has

b) lower initial setting time around 2 to 3 hours, but higher final setting time around 5 to 6 hours.

Mohamed Atia Abd elhady
by Mohamed Atia Abd elhady , مهندس , دلتا مصر للمقاولات

b) lower initial setting time but higher final setting time

SUBHASHISH BHATTACHARYA
by SUBHASHISH BHATTACHARYA , Asst. Manager-AutoCAD Drawing & Technical Documentation , Jindal Steel & Power Ltd.

b) Initial setting time is more than3 hours. Final setting time is about5 hours.

Therefore, it allows more time for mixing and placing operations. 