What is the rolling wave planning?

user-image
Question added by Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill
Date Posted: 2015/03/12
Dhawal Thakkar
by Dhawal Thakkar , Senior Engineer Projects , TDK Corporation

There are2 ways of planning

1) Waterfall and2) Rolling wave.

In waterfall method - You have the complete project plan well defined at the start.

where as in Rolling wave- On major activity are planned at the initial stage. later as the project progress , the detail plan is unfolded.

 

 