Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What do you think about the following contract item : “The detailed work program should be submitted 30 days after date of commencement.”?

As a planning engineer, what do you think about the contract item placed generally in most agreements: “The preliminary work program should be submitted to the supervisor/client within the15 days after signing the construction contract and the detailed program30 days after date of commencement.”?

user-image
Question added by Kunterhan Ozdemir , Senior Planning Manager , JASARA PMC
Date Posted: 2015/03/15
amir noor khan amir
by amir noor khan amir , Mechanical Maintenance supervisor , AISHA STEEL MILLS LIMITED

 

Excellent Maintenance and Troubleshooting experience in Plant rotating equipments like Pump, Compressors,  and other Have Machinery. Hands on experience in Replace defective parts of machines or adjust clearances and alignment of moving parts, Align machines and equipments using hoists, jacks, hand tools, squares, rules, vibe row pin pay row meter and plumb bobs. Laser Alignment Experience is a must.

 

Sanjeev Gupta
by Sanjeev Gupta , Manager Contracts & Procurement , Halliburton worldwide Ltd

Commencement of work might include preparation, mobilization, setting up site office.  In short all activities prior to starting the execution of work as per scope, drawing, design and specification

G S
by G S , Senior lawyer , National Union of Attorney at Law of Romania

Signing date and commencement date of the contract are different.

In FIDIC type of contracts, commencement date is the date at which precedent condition has all been fulfilled (like right of access to the construction site and possession of the site-given to Contractor by the Employer or Performance security received by the Employer from Contractor, Receipt of the advance payment - by the Contractor from Employer) and instruction to commence the works is received by Contractor.

So, only after the Contractor is in the possession of the site he is able to determine a detailed time program of works.

sugumaran Balakrishnan
by sugumaran Balakrishnan , SrPlanning Engineer , VA TECH WABAG LTD

This days period is to Determine the Critical logic , long lead procurement Items,Risk factors and the initial guidance to the project endeavor.

عبدالرحمن العتيبي
by عبدالرحمن العتيبي , متدرب , الهيئة العامة للمساحة

To be this decade because it shows the interaction of the second party and tax farming work illustrates the first party course of action and how it works