Register now or log in to join your professional community.
A- WIP Account
B- spoilage account
C- finished good account
D- None of answers above
A- WIP Account .......................
In Process Costing direct material is added to Work - In- Progress A/c. The reason - In Process Costing there is a cycle of continuous flow of raw material in various processing departments.
Answer option >>>>>>>>>>>>>>>>> A- Work in progress/Process Account
D-
WIP Account
Direct Material is add to Work in process Account
In the process costing method direct materials are add to WIP Account.
The direct materials add to the WIP accounts, so that
Materials are added to A. WIP account.
In Process Costing direct material is added to Work In Progress A/c. The reason - In Process Costing there is a cycle of continuous