The project manager then issues a change request.What should the change request authorize?
A. Additional resources using the contingency fundB. Escalation approval to use contingency fundingC. Team overtime to meet scheduleD. Corrective action based on causes
The case didn't talk about going above budget or behind schedule so far, I would agree with
D. Corrective action based on causes
My answer is option (D) CORRECTIVE ACTIONS
Corrective actions based on causes.
I choose option D. Corrective action based on causes
I also go with option D) corrective action based on cause......
Additional resources using the contingency fund
D is the solution to meet the accepted deadline.