Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed.

The project manager then issues a change request.What should the change request authorize?

A. Additional resources using the contingency fundB. Escalation approval to use contingency fundingC. Team overtime to meet scheduleD. Corrective action based on causes

user-image
Question added by Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.
Date Posted: 2015/03/27
Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The case didn't talk about going above budget or behind schedule so far, I would agree with

D. Corrective action based on causes

My answer is option (D) CORRECTIVE ACTIONS

Adeniyi Aderemi
by Adeniyi Aderemi , IT infrastructure team lead , Jetlink Limited

Corrective actions based on causes.

Deleted user
by Deleted user

 

 

  I choose option D. Corrective action based on causes

 

 

 

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

I also go with option D) corrective action based on cause......

George Karaparambil
by George Karaparambil , Manager, Financial Analysis , Kerala Ayurveda Ltd, KATRA GROUP

Additional resources using the contingency fund

Muhammad Sajjad Anwar
by Muhammad Sajjad Anwar , Manager MIS , FAUJI FOUNDATION

D is the solution to meet the accepted deadline.

Rabbson Chikuse
by Rabbson Chikuse , Driver , Not working

Option D is a priority because if you take corrective action based on causes the request can be of a great importance because at first you will identify the causes and came up with a solution.

More Questions Like This