Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

On what basis you decide that an activity should be defined as task based or resource based?

Duration type and the type of activity determines the way calculations are controlled in the system. How will you decide the duration type?

user-image
Question added by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture
Date Posted: 2013/08/02
Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

Task based activity is used when you require to load multiple resources working together for the activity and these resources use the activity calendar.
Resource based activity is used when u need to have multiple resources loaded for the activity which uses separate resource calendars and also these resources work independently and doesn't depend on the activity calendar.

Ali Harin
by Ali Harin , General Manager , Harinco For Contracting And Trading Company

Thank you Anisuddin for your valuble question.
The base at which an activity is to be defined as a task dependent activity ,is the case when the activity does not need any resource to be assigned to it or the resources that need to be assigned to it only use the activity calendar to define the activity dates and duration.
On the other hand an activity can be defined as a resource dependent ,if the resources calendars govern the definition of both dates and the duration of the activity.
Thank you Best regards

Deleted user
by Deleted user

Prioritizing the required tasks according to the importance and its due date

mohammed arif ahmed masood ali
by mohammed arif ahmed masood ali , HR ASSISTANT , gulf catering company

I always  give the priorty those who are urgent work we need to do first.

saima Iqbal
by saima Iqbal , Manager cash management operations , Head office Emaan Islamic Silk Bank LTD

Task to do first based on the closest deadline as per my schedule.

RODELLO RAMOS
by RODELLO RAMOS , Sr. Administrative Officer , Academy of Saint Andrew - Caloocan (ASAC), Inc.

Prioritizing the most important task and consider the date due.

Nuwan fernando
by Nuwan fernando , Floor Supervisor , LAVAL LOUNGE) ACC Group

Resource based activity is used when u need to have multiple resources loaded for the activity which uses separate resource calendars and also these resources work independently and doesn't depend on the activity calendar.

Umer Syed M
by Umer Syed M , Manager Administration

As a Manager, you should be able enough to understand the processes being done under your command and how much time it takes by your subordinates to perform the task.

Keeping in view that all employees are not equally talented you need to acertain which task is best to be given as a task to a resource.

 

 

Prem Ballabh Naugain
by Prem Ballabh Naugain , Senior Administrator/ Administration Manager , Gulf Industrial & Marine Services Company W..L.L.

Make schedule of the priority works and act accordingly

Ashfaq Anwar
by Ashfaq Anwar , Assistant Admin , Education

According to the situation work can be done. mostily work done in a group is best but on some extent completion of work require individual effort. 

More Questions Like This