Register now or log in to join your professional community.
please tell me how to Schedule % complete in primavera p6.
many Ways in Case u want to prepare ur s Curve base on time or cost
1-base on time just add resource with unit rate1 to all activity total budget unit will be same the duration
2- base on effort or cost u can export ur file to excel file and change the total budget units as u want as explained before
Thanks for asking me. i would like to give one of the way to generate S Curve in Primavera as in your case resource is not loaded.
1. Create a non labour resourse with unit rate as1 INR/SAR and assigned this resourse in to all the activities.
2. Export the primavera file in xls(excel format)
3. Calculate the weightage for each activity as per your price schedule (Sales / Cost) and to avoid the minor values, total summation of weightage shall be10,000 or100,000.
4. Use Vlookup formula to put the calculated in budgetted unit of respective activity id.
5. Import into Primavera, then add two columns Schedule percentage & performance percentage
6. Schedule percentage is nothing but the planned percentage as per Baseline and performance percentage is actual percentage.
Hope the answer for your question
Use the global change to assign weightage to your activities as multiples of1 based on your estimated manpower utilization
thus you can generate an estimated S curve
If resources are not loaded we have to prepare S Curve based on cost loading.
As explained by ASARUDEEN SOWKATH ALI
You can get more information on it from this well-elaborated article