When are update progress and apply actual get used in P6 schedule?

user-image
Question added by Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date Posted: 2013/08/04
Anisuddin Siddiqui
by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

Once a Schedule has been completed, approved and a baseline set then you may start updating it based on the execution in case the project has already started.
The actuals are applied once details are collected from site.