Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What does Primavera use? PERT or CPM?

user-image
Question added by Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date Posted: 2013/08/04
Anisuddin Siddiqui
by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

The system is capable of both.
It shows a PERT diagram of activities when you ask for it.
In the bar chart mode CPM is used and depends on how effectively you build the relationships.

Riham Mostafa
by Riham Mostafa , Planning/Cost Control Engineer , Cleopatra for Integrated Touristic Investment and Real Estate Co.

Primavera uses CPM method for calculation.
Yet it can present the network diagram using either PERT or Bar Chart but they are considered as a way for presentation not calculation

FAWAS KANIYATHU KANDI
by FAWAS KANIYATHU KANDI , Business Analyst , Al Jazeera Technical Oil Field Supplies

in primavera it uses mainly critical path method cpm

Mohamed  Ali PhD Cand  MSc PMP PMISP
by Mohamed Ali PhD Cand MSc PMP PMISP , Project Control Manager , SEDER GROUP

BOth

 

Rahim Rajan
by Rahim Rajan , Ombudsman , Mohtasib

pert

Tanveer Ahmad Niazi
by Tanveer Ahmad Niazi , CEO (Self-employed) , Project Management Training & Consultant

Anisuddin and Riham explained it well to understand CPM please go to http://www.oracle.com/us/products/applications/042744.pdf

Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

It's using PERT

Hammad Noor Syed
by Hammad Noor Syed , Planning Engineer , Ansaldo-STS

We can use both techniques but usually CPM is used more than PERT.

Ali Harin
by Ali Harin , General Manager , Harinco For Contracting And Trading Company

Thank you Binil for your valuable question , both CPM and PERT is used by the program to build the activities net work on which you can be able to deal with all the data of the project and use the trace logic technique to develop good smart relationships between the activities.
Thank you .
Best regards

Gonzalo Alfaro
by Gonzalo Alfaro , Teacher , Universidad Santo Tomás

CPM

Mohammad Adel Abd-alaziz
by Mohammad Adel Abd-alaziz , Deputy Operations Director & TPM Facilitator , Egyptian Starch & Glucose Manufacturing Company

uses pert to reoresent CPM

More Questions Like This