How to assign multiple labor resource in Primavera p6. eg- 80 helper, 30 mason, 30 carpenter. do i need to write name of each or is there other way

user-image
Question added by Deleted user
Date Posted: 2015/04/26
AHAMED MUHAMMED KUNJU
by AHAMED MUHAMMED KUNJU , Sr. Planning Engineer , Beaver Gulf Contracting LLC

WRITING NAMES IS NOT VALUABLE CRITERIA FOR ANY CALCULATION IN PRIMAVERA . SO, JUST ADD TRADE NAME AND NUMBER OF LABORS, THAT'S IT.

 

murali kurmana
by murali kurmana , Sr.Planning Engineer , Galfar Engineering & contracting SAOG

You need to creat Resource grouping in trade wise