Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During the execution of a project, a risk is identified by a team member. This newly identified risk is currently not in the Risk Register.

As a Project Manager, what is the first action you would take after being notified of the risk?

 

a) Discuss the risk with the team to ascertain the impact and probability of the risk

b) Analyze the risk.

c) Hold a meeting with the team leads to determine dependency and secondary risks.

d) Update the Risk Register.

user-image
Question added by Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer
Date Posted: 2015/04/28
Nancy Refai
by Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer

I would go for option B and analyze the risk. 

Because according to the ISO31000 risk management guidelines the risk analysis process includes both A and C options and will pave the way for completion of option D 

Christeena Shiju
by Christeena Shiju , Visa & Immigration Consultant , New Land Chase Immigration

I would first analyze the risk. And then get into meeting with the team to discuss on the impact and probability. Once the risk is found relevant, the Risk Register will be updated.

Shaik Mahaboob Subhani
by Shaik Mahaboob Subhani , Strategy IT Head , Annapurna Finance

1. Analyze the Risk.

2. Discuss with Team and if it required with Stake holders to ascertain the impact/probabilities. 

3. Prepare the mitigation of this Risk.

4. Update the Risk Register. If this Risk is impacting any schedules and agreed by timelines up date the project plan.

 

 

MUHAMMED HARIS MI
by MUHAMMED HARIS MI , Senior Audit Staff , Saud Bahwan Group LLC.

Ans. Option B is the right choice (Analyse the risk)

Deleted user
by Deleted user

a) Discuss the risk with the team to ascertain the impact and probability of the risk

However Creation of a Contingency Plan to deal with the risk should it occur.Taking early steps to reduce the probability of an adverse risk occurring may be more effective and less costly than repairing the damage after a risk has occurred.

However, some risk mitigation options may simply be too costly in time or money to consider.

 

MUHAMMAD YASIR ABDULLAH
by MUHAMMAD YASIR ABDULLAH , GENERAL BANKING OFFICER , MCB BANK LIMITED

I THINK DISCUSS IT WITH THE TEAM AND TAKE STEPS TO REDUCE SUCH TYPE OF RISKS

George Karaparambil
by George Karaparambil , Manager, Financial Analysis , Kerala Ayurveda Ltd, KATRA GROUP

 D.

Update the Risk Register in the system

S. M. Zahidur Rahaman
by S. M. Zahidur Rahaman , Manager Marketing , Helt Rent Services Aps

As a manager i must stop the work in progress instantly and registered the risk.After that i should go for a meeting with each and every member of the project that they should aware about what constitutes a risk to the project or factor that could potentially impact the project in a positive or negetive way.

Aamar Sharif
by Aamar Sharif , Deputy Director (Tech) , DGPR, Government of Punjab

All of the above with sequence B- A- C- D but D with the addition of all secondary risks and depedency.

Bhavin Mehta CCP(CCE), PMP
by Bhavin Mehta CCP(CCE), PMP , Assistant Manager , Larsen and Toubro Ltd

D- Update the risk register is the first thing to be done as per PMBOK

BASIT  JAVAID
by BASIT JAVAID , Area Service Engineer , Starlinger &Co

Analyze the risk first... will my first priority.

More Questions Like This