a. Increased overall level of activity.
b. Customer’s requirement for early completion of job.
c. Management’s failure to include the job in the
production schedule.
d. Management’s requirement that the job be completed
before the annual factory vacation closure.
Answer b. Customer’s requirement for early completion of job.
Answer B is the right option by customer 's requirement .