(a) Time on the horizontal; the activities to be scheduled on the vertical(b) Time on the vertical; project completion on the horizontal(c) Time on the horizontal; project completion on the vertical(d) Time on the vertical; the activities to be scheduled on the horizontal(e) Time on either; the activities to be scheduled on the other.
(a) >>>>>>>>>>>>> Time on the horizontal; the activities to be scheduled on the vertical
(a)
Reason : A Gantt chart is essentially a bar graph with time on the horizontal axis and the activities to be scheduled on the vertical axis.
Hence from above discussion, we can infer that option (a) is correct
(A) Thank You.
(a) Time on the horizontal;>>>>>>>>>>>>>>>>>>>>>>>
the activities to be scheduled on the vertical